Benchmark Performance Metrics for Integrated Project Delivery
• The processing time for change orders on an integrated design project was averaged at 1.9 weeks where a typical project processing time averaged at 4.8 weeks. The average RFIs per million was 3.9 on an integrated project compared to an average of 8 on a non-integrated project.
This study fills the gap in project delivery system research by evaluating the effects of IPD on building construction projects across a wide range of performance metrics from the perspective of general contractors and construction managers. This research demonstrates that IPD/near-IPD outperformed non-IPD projects with respect to performance in communication, change management, and business performance areas.
Hanna, A. (2016). Benchmark Performance Metrics for Integrated Project Delivery. Journal of Construction Engineering and Management, 142(9).
Add comment
Log in to post comments